PRINCE2® wiki

Progress

The progress practice of PRINCE2 is about measuring performance and determining how we’ve performed compared to plans and what we have to do if there are any deviations.

Purpose

The purpose of the progress practice can be summarized in three key objectives:

Progress is about tracking actual performance against the plan, ensuring the project remains viable, and managing deviations effectively.

The following principles have the biggest impact on this practice:

Progress and controls

Progress refers to tracking and controlling where the project stands compared to the plan. This applies to the project plan, stage plan, and work packages.

Each layer of management monitors the progress of the layer below it using progress controls. For example:

The layer above can:

Exceptions and tolerances

An exception occurs when it’s forecast that the project will deviate beyond agreed tolerance levels.

Tolerances define the acceptable range of deviation from the plan’s target. For example, a project scheduled to take 6 months might have a ±1 month tolerance. Tolerances can apply to all seven project variables: Time, cost, quality, scope, benefits, risk and sustainability.

The following table shows where tolerances for each variable are defined:

variableproject level tolerancesstage level toleranceswork package level tolerances
timeproject planstage planwork package
costproject planstage planwork package
scopeproject planstage plan (agile)work package
qualityproject product description & product descriptionsNANA
benefitsbusiness casestage planNA
riskbusiness casestage planwork package
sustainabilitybusiness casestage planwork package

Without tolerances, the project manager would have to escalate every issue to the project board, leading to unnecessary workload for both the project manager and the project board.

Setting tolerances allows the project manager to handle minor issues, only escalating bigger problems and saving time for both parties.

PRINCE2 approach to progress

Progress in PRINCE2 involves comparing actual progress with the project’s performance targets: Time, cost, quality, scope, benefits, and risk.

PRINCE2 ensures control through four key mechanisms:

These controls are defined early in the project and documented in the project initiation documentation under the progress section.

Delegation of authority

The following is how different layers of management delegate and escalate:

Raising exceptions

Raising an exception is directly linked to the PRINCE2 principle of manage by exception. An exception occurs when a tolerance is exceeded or is forecast to be exceeded.

The key question here is: “When is an exception raised, and by whom?”

By clearly defining tolerances and using exceptions, PRINCE2 ensures that issues are flagged appropriately, allowing for better control and timely intervention.

The 3 project board controls

The project board has three main controls available to them to manage the levels below.

The 3 project manager controls

Similar to the project board controls, but at the project manager level, these three controls include:

Use of management stages for control

Management stages break a project into smaller, more manageable sections, each with decision points to ensure the project stays on track. The project manager is responsible for overseeing the execution of these stages.

Why are management stages important for the project board?

By defining tolerances, the project board empowers the project manager with day-to-day authority to manage the stages effectively, allowing for faster decision-making without needing constant oversight.

Minimum stages in a project

At a minimum, every PRINCE2 project must have two stages:

For a very short project, like one lasting just two days, the first day would be used for the initiation (defining what needs to be done, how it will be done, and by whom). The second day would be dedicated entirely to product creation.

Deciding on the number of stages

The number of stages in a project depends on several factors, and it’s a balancing act. Key considerations include:

Length of stages

The length of each stage largely depends on the project’s complexity and risk level. More complex projects or those with higher risk may benefit from shorter stages, while simpler projects or those done before may have longer stages.

PRINCE2 offers some points to guide the decision on stage length:

Types of control

In PRINCE2, controls are divided into two key types:

Capturing and reporting lessons

One of the core principles of PRINCE2 is learning from experience. The project team is responsible for actively seeking, recording, and applying lessons throughout the project. The term “sought” emphasizes that everyone involved in the project should make an effort to identify lessons that could improve the project’s performance. Once identified, these lessons are documented in a lessons log, which serves as a valuable record of experiences and improvements.

Lessons can cover various aspects, including communication strategies, supplier management, document tailoring for specific project types, and best practices for product breakdown structures. The project manager continuously adds new insights to the lessons log as the project progresses, ensuring that valuable information is captured and shared.

At the end of the project, a lessons learned report is created to summarize these insights and document them for future projects. In larger projects, a lessons learned report might be created earlier, such as during the managing a stage boundary process, to share knowledge that could benefit ongoing or upcoming stages.

By capturing and applying lessons, PRINCE2 projects enhance their ability to deliver successful outcomes while continuously improving the project management process.

Reports

Reports communicate progress information and help decide how to control a project. The following are the PRINCE2 reports:

Roles and responsibilities

—o—

Written by Frank Turley.

If you have questions or doubts after using this wiki, you can ask for help on the Facebook or LinkedIn study groups.