Product Status Account

The Product Status Account provides information about the state of products within defined limits. The limits can vary. For example, the report could cover the entire project, a particular stage, a particular area of the project, or the history of a specific product. It is particularly useful if the Project Manager wishes to confirm the version number of products.

The Product Status Account is derived from the Configuration Item Records and the Stage Plan. A Product Status Account can take a number of formats, including: Document, spreadsheet or report from a database; Output from a project management tool.

The following quality criteria should be observed: